Shaikpet flyover work to be completed by GHMC by the end of the year
Shaikpet flyover work to be completed by GHMC by the end of the year
Share:

Hyderabad: Proposed in 2017 by the Greater Hyderabad Municipal Corporation's Strategic Road Development Plan at an estimated cost of Rs 333.55 crore, the Shaikpet flyover is to be completed by the end of the year. The six-lane two-way flyover, with a length of 2.8 km, starts at Tolichowki and ends at Malkam Cheruvu. According to SRDP officials, the work was going on at a good pace and almost 85 per cent was finished.

Major portions like six slabs and a ramp are pending, besides laying of the slab. If they are finished electrical work and installing streetlights on either side of the flyover will be taken up. The flyover will facilitate crossing junctions of Seven Tombs, Filmnagar, OU Colony and Whisper Valley. It has been planned to ensure smooth flow of traffic towards IT hubs. 

The officials have set the target to finish the work and likely to get inaugurated by December-end. At the initial stage of the flyover there was a delay on account of land acquisition and even the area traffic. All the hurdles have now been cleared. Only construction work and installing lights are the major pending tasks, said a source.

 

Kinnaur Landslide tragedy: President Ram Nath Kovind expresses condolences

Reports of terror attack on RSS and BJP leaders, high alert across Punjab

This many new corona cases in Puducherry, 1803 patients died so far

Join NewsTrack Whatsapp group
Related News